How Cheenta works to ensure student success?
Explore the Back-Story

Time & Work Problem | PRMO-2017 | Problem 3

Try this beautiful problem from PRMO, 2017 from Arithmetic based on Time & Work.

Time & Work Problem | PRMO | Problem 3


A contractor has two teams of workers: team A and team B. Team A can complete a job in 12 days and team B can do the same job in 36 days. Team A starts working on the job and team B joins A after four days. Team A withdraws after two more days. For how many more days should team B work to complete the job?

  • \(24\)
  • \(16\)
  • \(22\)
  • \(18\)

Key Concepts


Arithmetic

Unitary process

Work done

Check the Answer


Answer:\(16\)

PRMO-2017, Problem 3

Pre College Mathematics

Try with Hints


At first we have to find out A's 1 days work and B's 1 days work.next find out A and B both together 1 day's work .

Can you now finish the problem ..........

Team A completes job in 12 days and Team B completes job in 36 days

1 day work of team A =\(\frac{1}{12}\)

1 day work of team B=\(\frac{1}{36}\)

1 day work of team A and team B (when they both work together \(\frac{1}{12} +\frac{1}{36}\)=\(\frac{1}{9}\)

Now according to question,
Let more number of days should team B works to complete the job be x days

\(4 \times \frac{1}{12} +2 \times \frac{1}{9} + x \times \frac{1}{36}=1\)

\(\Rightarrow x=16\)

Subscribe to Cheenta at Youtube


Try this beautiful problem from PRMO, 2017 from Arithmetic based on Time & Work.

Time & Work Problem | PRMO | Problem 3


A contractor has two teams of workers: team A and team B. Team A can complete a job in 12 days and team B can do the same job in 36 days. Team A starts working on the job and team B joins A after four days. Team A withdraws after two more days. For how many more days should team B work to complete the job?

  • \(24\)
  • \(16\)
  • \(22\)
  • \(18\)

Key Concepts


Arithmetic

Unitary process

Work done

Check the Answer


Answer:\(16\)

PRMO-2017, Problem 3

Pre College Mathematics

Try with Hints


At first we have to find out A's 1 days work and B's 1 days work.next find out A and B both together 1 day's work .

Can you now finish the problem ..........

Team A completes job in 12 days and Team B completes job in 36 days

1 day work of team A =\(\frac{1}{12}\)

1 day work of team B=\(\frac{1}{36}\)

1 day work of team A and team B (when they both work together \(\frac{1}{12} +\frac{1}{36}\)=\(\frac{1}{9}\)

Now according to question,
Let more number of days should team B works to complete the job be x days

\(4 \times \frac{1}{12} +2 \times \frac{1}{9} + x \times \frac{1}{36}=1\)

\(\Rightarrow x=16\)

Subscribe to Cheenta at Youtube


Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Knowledge Partner

Cheenta is a knowledge partner of Aditya Birla Education Academy
Cheenta

Cheenta Academy

Aditya Birla Education Academy

Aditya Birla Education Academy

Cheenta. Passion for Mathematics

Advanced Mathematical Science. Taught by olympians, researchers and true masters of the subject.
JOIN TRIAL
support@cheenta.com
Menu
Trial
Whatsapp
Math Olympiad Program
magic-wandrockethighlight